TMT spol. s r.o. Chrudim
Transport and Handling Equipment
Conveyors and conveyor systems

News

At the beginning of February 2010 was put into test operation formatting  line of cement-splinter boards. The line was under the reconstruction since April 2009. Cement-splinter boards are transported to drying kiln where they are dried and than cut by formatting line to the required sizes. They are transferred to pallets due to manipulators and dispatched. The installation itself of this line took place since the beginning of December 2009 till the end of February 2010.